How to use Backward Deadline PlannerSteps, an example, the math and common questions

How to use it

  1. Pick a template, like a trip, wedding, move, home purchase, baby, college or taxes.
  2. Set the deadline date.
  3. Adjust steps and lead times to fit your situation.
  4. See the start-by date for every step and add them to your calendar.

An example

A trip abroad on June 1 needs a passport. Passport processing takes about 6 to 8 weeks, so the start-by date is mid-March. Photos come first, so they move earlier.

Questions people ask

What is the critical chain?
The steps with no slack. Any delay there moves your deadline.
Does it count business days?
Yes, for steps like government processing.
Can I export it?
Yes. Download a calendar file.

The math

Start-by dates
Working backward from the deadline, each step must finish before anything that waits for it can start. Its start-by date is the latest it can begin without pushing the deadline.
Critical chain
Steps with zero slack. If any one of these slips a day, so does your deadline.
Late check
Working forward from today, it checks whether finishing everything in order still beats the deadline.
Buffer
Applied only to ⏳ steps, because those are the ones you can’t speed up.

Good to know

How to plan backward from a deadline

Most missed deadlines aren't caused by slow work. They're caused by starting the one slow step too late.

List every step and its lead time

Include the waiting, like passport processing, shipping and other people's approvals. Those are usually the longest steps.

Note what waits on what

You can't submit a passport application before you have photos. Each dependency pushes start dates earlier.

Work backward

Start from the deadline and subtract each step's time, following the dependencies. That gives every step a latest start date.

Find the critical chain

Steps with no slack are the ones where any delay moves the deadline. Watch those closely and start them first.

Add a buffer where you have no control

Government processing and shipping run late. Pad those steps, not the ones you control.